Construction Updates

Construction started on October 20, 2025. Works in 2025 include:

  • Establish contract signing and PVMS

  • Temporary electrical work to provide power to Highway 7 high mast lighting during works

  • Remove concrete gore area and curb and gutter on S-E/W ramp to permit Stage 2B traffic

  • Reconstruct Victoria and Bruce Street intersection

  • Construct sanitary and storm sewers

  • Demolition of Frederick Street Bridge is scheduled for December 6, 2025, weather permitting and subject to change