Construction Updates
Construction started on October 20, 2025.
Work completed in 2025 and 2026 to date:
Establish contract signing and PVMS
Temporary electrical work to provide power to Highway 7 high mast lighting during works
Remove concrete gore area and curb and gutter on S-E/W Ramp to permit Stage 2B traffic
Reconstruct Victoria and Bruce Street intersection
Construct sanitary and storm sewers
Demolition of Frederick Street Bridge took place on December 6, 2025
Substructure work completed
Peir Columns completed
Formwork/falsework installation on-going
Anticipated remaining work in 2026:
Complete formwork/falsework
Complete bridge deck
Highway staging work to reopen lanes on Hwy 7/85 prior to winter shutdown
Anticipated remaining work 2027:
Complete remain bridge work (barrier walls, expansion joints, approach slabs)
Bridge deck waterproofing and surface course paving
Complete final electrical work
Complete final municipal roadworks